David Morton (Larbert) Ltd successfully delivered the full demolition and site clearance of the redundant grain store facility located in Loanhead, Midlothian. The project was completed within the 16-week programme and in full compliance with all statutory and client requirements.

Key Project Components:

Asbestos Removal: All asbestos-containing materials (ACMs) were removed in accordance with CAR 2012 regulations. This included both licensed and non-licensed materials, with strict adherence to HSE guidelines and environmental controls.

Demolition Works: The project involved the dismantling and demolition of all above-ground structures, including grain silos and associated buildings, followed by the removal of all below-ground foundations and floor slabs.

Environmental Controls: Dust, noise, and vibration were continuously monitored and controlled using best practicable means. All works were carried out with minimal disruption to neighbouring industrial and residential areas.

Waste Management: Over 95% of demolition arisings were recycled or repurposed, in line with Zero Waste Scotland and SEPA guidelines.

Health & Safety: The project was completed with zero reportable incidents, supported by robust site inductions, exclusion zones, and daily safety briefings.

Site Restoration: Upon completion, the site was backfilled, graded, and left in a clean, level, and hazard-free condition, ready for future development.

Challenges Overcome:

The presence of live services and adjacent operational infrastructure required careful planning and coordination.

The removal of asbestos cement roofing from high-level structures was managed using a combination of MEWPs and controlled “wet and drop” techniques to minimise fibre release.

The project team maintained flexibility to accommodate unforeseen findings, including additional ACMs and structural complexities. This project stands as a testament to David Morton Ltd’s commitment to safe, sustainable, and efficient demolition practices, and further reinforces our reputation for delivering complex projects on time and to the highest standards.

Straiton Silos grain-1